Emrill Services, the multi-award winning UAE-based integrated facilities management provider, has announced the appointment of a new CEO and CFO. The firm’s previous technical director, Stuart Harrison, has been promoted to chief executive officer, effective immediately, and will be based at Emrill’s Dubai head office.   Harrison’s appointment is a result of his proven track […]

Downtown Dubai gets a deep-clean thanks to Emrill’s eco-friendly pavement cleaner

Emrill Services, the multi-award winning UAE-based integrated facilities management provider, has unveiled the latest addition to its cleaning services line-up – the CMAR NC 286R hot water pavement cleaner with suction, the first of its kind in the UAE.   The new machine was unveiled at a handover ceremony in Downtown Dubai, which was attended […]

View All News >
Case Study: Dubai Marina Towers’ 26% Energy Savings
 

Emrill Services is a UAE-based energy and facilities management company that provides, among others, energy performance contracting (EPC) services. 

 

The firm's flagship EPC project has been the Dubai Marina Towers, where initial work started in 2015, with energy savings of 25% anticipated at the time. 

 

 

In the last 12 months, the EPC scheme has surpassed forecasts and delivered average energy savings of 26%. 

 

 

Stuart Harrison, technical director at Emrill Services, reveals the company's programme to achieve these energy savings. 

 

 

"As the towers are located in a premium residential area, it was important for Emrill to work in harmony with the site team and owners' association to ensure seamless project results," he tells ConstructionWeekOnline.

 

 

"The Dubai Marina Towers were fully occupied at the time, so careful planning was required to prevent loss of comfort or facility to residents during the installation and commissioning phases. 

 

 

"Emrill successfully designed and implemented a new building management system (BMS), along with replacement smart sensors and intelligent control equipment. 

 

 

"As part of a fully customised controls strategy, the upgrade work allowed intensive monitoring and controlling of the entire HVAC system, providing greater responsiveness to prevailing weather conditions and fluctuations in building and tenant demand.

 

 

"The hybrid BMS also optimised the size of equipment operating concurrently." Harrison says Emrill's contract also included "a range of energy efficiency upgrades". He continues: "[This covered] chiller controls; chilled water pumping; BMS; AHU [air handling unit] and VFD [variable frequency drive] control; and heat recovery wheel works, as well as changes to various de-humidification cooling and lighting systems.

 

 

"The project was completed and handed over to the client in March 2016, and ever since, Emrill has continued to oversee the management and improvement of these new systems, in cooperation with its specialist energy efficiency arm, Emrill Energy, and other partners."

 

 

Article Source: Construction Week Online

Link: http://www.constructionweekonline.com/article-44397-case-study-dubai-marina-towers-26-energy-savings/